A greenfield rolling mill needed its structural frame fabricated, delivered and erected inside a fourteen-week window dictated by the equipment supplier. We ran two shifts, sequenced deliveries to match the erection programme, and finished four days ahead of the critical path.
The Challenge
The equipment supplier fixed a fourteen-week window and the site had no laydown area, so nothing could be delivered early.
Our Solution
We built to a just-in-time delivery schedule sequenced against the erection programme, holding finished steel in our own yard and releasing it lift by lift.